Ag Partners Begins Rebuilding Royal, IA Location

After last August's explosion, company began demolition last week with new construction beginning in 2021

Under construction 2891888 1920

After an explosion happened at Ag Partner's Royal, IA facility last August, the cooperative is getting ready to rebuild.

Royal Explosion Pic Credit Ag Partners Llc
Photo: Ag Partners LLC

Demolition of the main complex started last Friday and will be completed by the end of December.

The rebuilding process will begin around the start of 2021. The new structure will include four steel bins, two 15,000 bushel/hour legs, and two pits to the south of the complex along with necessary towers and catwalks.

The new design will continue to provide fast unload times in the fall with a capacity to unload grain at 60,000 bushels/hour between the two southern unload pits and the northern high-speed pit.

The August explosion happened in a part of the elevator which houses both corn and soybeans. The elevator was mostly empty at the time of the explosion.

Despite the extensive damage at the facility, no one was injured.