A. Demolition, Retrofit and New Equipment Installation

  • Remove existing reclaim equipment, top transfer drags and distributor, supports, spouting and bridge
  • Extend receiving and shipping bucket elevators
  • Install two new gate valves and a lined u-trough to existing bulkweigher
  • Two new 12,000-bushel/hour transfer drag conveyors from each leg to the new dual inlet distributor
  • Install a new “Schlagel” dual inlet, 24-duct, electric distributor
  • Install new 24,000-bushel/hour reclaim drag and retrofit gate valves to the bucket
  • Install new dust collection baghouse and support structural

B. Structural Supports & Access

  • Install a new structural support bent and top transfer drag bridge
  • Install new access to the receiving leg and shipping leg extensions
  • Install a new electric 500-pound capacity manlift and steel shaftway